Current Status

Design plans are at 60% and the right-of-way acquisition process has started as of Nov. 20, 2023.

Purpose of the Project

This project is part of the Southern Rivers Flood Protection Program Master Project. It includes design, property acquisition, and construction to raise New Bridge Road, construct a box culvert under New Bridge Road, and road and shoulder improvements on Sandbridge Road to increase safety at the New Bridge Road/Sandbridge Road intersection and to reduce the need for road closures due to flooding from the adjacent Ashville Creek.

Quick Facts

Project Cost

Design:

$750,000

Site Acquisition:

$620,000

Private Utility Adjustments:

$450,000

Construction:

$6,170,000

Total:

$7,990,000

Project Schedule

Design:

October 2022 through January 2027

Site Acquisition:

January 2024 through August 2026

Private Utility Adjustments:

February 2027 through July 2027

Construction:

August 2027 through September 2029

Project Contacts

Please contact the Stormwater Engineering Center with any questions or concerns regarding the Southern Rivers Watershed and stormwater-related activities and assessment. Questions or concerns regarding the Roadway Construction Projects can be directed to Project Manager Ali Salim, P.E. at (757) 385-5639 or ASalim@vbgov.com.