Current Status & Next Steps

This project is currently under evaluation as part of the FY26 budget planning process. This project is funded by CIP 100058.

Purpose of the Project

The purpose of this roadway improvement project is to increase capacity and safety improvements for vehicles, bicyclists and pedestrians through the Centerville Turnpike corridor. The project will include:

  • Design of roadway and drainage improvements to widen the road to four 11-foot travel lanes, provide a raised median and curb and gutter, 4-foot bicycle lanes, 5-foot concrete sidewalk, and 8-foot asphalt sidewalk for pedestrian users.
  • Complete a Master Drainage Study of Watershed 12 (Stumpy Lake), including existing facilities, assessment of tail-water conditions, consideration for sea-level rise, and development of proposed improvements to the watershed.
  • Incorporate results of the Master Drainage Study into the design of the stormwater conveyance system for Centerville Turnpike Phase III as well as the design of stormwater management facilities that consider both water quantity and quality.
  • Prepare all required environmental permitting documents, coordinate agency review, and secure necessary permits from appropriate regulatory agencies.
  • Complete Traffic Analysis Study of project area to support permitting and design activities including Access Management Study and signal warrant analysis.
  • Design new and upgraded traffic signals as required.
  • Design of relocated public utilities, including City water and sanitary sewer facilities, including connections as necessary to HRSD facilities, preparation of maintenance of service plans.

Resources

Copies of the following resources can be requested by contacting Project Manager, Wesley M. Parker at WesParker@VBGov.com.

  • Project Plan Sets (December 2, 2020)
  • Cross Sections (December 1, 2020)
  • Categorical Exclusion (CE) Documentation (April 16, 2020)
  • Documentation of FHWA Review (April 24, 2020)
  • Air Quality Assessment (January 2019)
  • Noise Analysis Technical Report (August 2019)
  • Virtual Public Hearing Presentation (December 10, 2020 – January 21, 2021)

Quick Facts

Project Phase

Cost

Schedule

Project Phase

Design

Cost

$2,437,874

Schedule

July 2017 to March 2026

Project Phase

Site Acquisition

Cost

$4,715,636

Schedule

February 2024 to October 2025

Project Phase

Public Utility Adjustments

Cost

$1,890,772

Schedule

October 2025 to October 2026

Project Phase

Construction

Cost

$52,527,356

Schedule

February 2027 to June 2029

Project Phase

Total Cost

Cost

$61,571,638