Centerville Turnpike Phase III
Increasing capacity and improving safety for vehicles, bicyclists and pedestrians through the Centerville Turnpike corridor.
Increasing capacity and improving safety for vehicles, bicyclists and pedestrians through the Centerville Turnpike corridor.
This project is currently under evaluation as part of the FY26 budget planning process. This project is funded by CIP 100058.
The purpose of this roadway improvement project is to increase capacity and safety improvements for vehicles, bicyclists and pedestrians through the Centerville Turnpike corridor. The project will include:
Copies of the following resources can be requested by contacting Project Manager, Wesley M. Parker at WesParker@VBGov.com.
Project Phase
Cost
Schedule
Project Phase
Design
Cost
$2,437,874
Schedule
July 2017 to March 2026
Project Phase
Site Acquisition
Cost
$4,715,636
Schedule
February 2024 to October 2025
Project Phase
Public Utility Adjustments
Cost
$1,890,772
Schedule
October 2025 to October 2026
Project Phase
Construction
Cost
$52,527,356
Schedule
February 2027 to June 2029
Project Phase
Total Cost
Cost
$61,571,638