Current Status

The contractor was issued notice to proceed on May 1, 2025.

Early project activities include:

  • Obtaining permits and approvals on shop drawings and materials.
  • Establishing survey control.
  • Installing erosion control measures.

Work will occur day and night, with lane closures scheduled at night to minimize disruptions to traffic. Dominion Energy is relocating some of the electrical distribution infrastructure ahead of the roadway work.

Key Project Features

  • Improving vehicular and pedestrian traffic flow and safety in the roadway and intersections.

  • Storm drainage upgrades.

  • Eight-foot sidewalks and on-street bike lanes.

  • Enhancing the corridor with aesthetic elements such as landscaping and lighting.

  • Relocating some power lines underground or to new overhead locations.

Quick Facts

  • Contractor notice to proceed date: May 1, 2025
  • Contract completion date: Oct. 12, 2028
  • Construction contract value: $67 million
  • Total project cost: $85 million