Current Status

The pedestrian sidewalk along eastbound Shore Drive is closed between Vista Circle and Starfish Road for demolition and grading work, stormwater improvements, road construction, and curb, gutter, and sidewalk installation. Pedestrians will be detoured to the westbound side of Shore Drive.  

The pedestrian sidewalks on the eastbound lane of Shore Drive (inland lane or lane furthest from the ocean) between Vista Circle and Starfish Road are closed due for construction. Pedestrian traffic should utilize the sidewalk on the westbound lane of Shore Drive (closest to the ocean) by using the crosswalks located at the Starfish Road and Vista Circle intersections. Closed sidewalks are marked with red arrows, and the detour route and crosswalks with green arrows.

Pedestrian detour along Shore Drive. Closed sidewalks are marked with red arrows and the detour route with green arrows. Crosswalks are at the Starfish Road and Vista Circle intersections.

Summer construction activities include:

  • Kevcor has installed the new sewer force main along Shore Drive to West Great Neck Road. A tie-in to existing HRSD sewer lines is planned for October.
  • Water main installation continues during day and night shifts and is expected to be complete by Fall 2026.
  • Stormwater improvements are continuing.

From May 1 to Sept. 30, lane closures are anticipated only during the night shift. Daytime closures are not expected to resume until Oct. 1, 2026. 

Project completion is currently scheduled for May 24, 2029. 

Construction can generate noise, light, dust and other inconveniences; however, crews are working to minimize these impacts as much as possible. Thank you for your patience and support, as we make improvements that will benefit the Shore Drive community for years to come. 

Updated Aug. 13, 2026

Key Project Features

  • Improving vehicular and pedestrian traffic flow and safety in the roadway and intersections.

  • Storm drainage upgrades.

  • Eight-foot sidewalks and on-street bike lanes.

  • Enhancing the corridor with aesthetic elements such as landscaping and lighting.

  • Relocating some power lines underground or to new overhead locations.

Quick Facts

  • Contractor notice to proceed date: May 1, 2025
  • Contract completion date: May 24, 2029
  • Construction contract value: $70 million
  • Total project cost: $91 million