Current Status

A new traffic pattern for the eastbound lanes between Vista Circle and Beech Street is expected in mid-April. Pedestrian traffic will be rerouted in the same area using existing crosswalks. Spring construction activities include:

  • Hampton Roads Sanitation District (HRSD) sewer force main has been installed along Shore Drive to West Great Neck Road. Tie-in to existing sewer lines is scheduled for May.
  • Water main installation continues during day and night shifts and is expected to be complete by summer 2026.
  • Stormwater improvements are continuing.
  • New temporary traffic signals are being installed ahead of the upcoming new traffic pattern.

From May 1 to Sept. 30, lane closures are anticipated only during the night shift. Daytime closures are not expected to resume until Oct. 1, 2026.

Project completion is currently scheduled for late 2028.

Construction can generate noise, light, dust and other inconveniences; however, crews are working to minimize these impacts as much as possible. Thank you for your patience and support, as we make improvements that will benefit the Shore Drive community for years to come.

Updated April 9, 2026

Key Project Features

  • Improving vehicular and pedestrian traffic flow and safety in the roadway and intersections.

  • Storm drainage upgrades.

  • Eight-foot sidewalks and on-street bike lanes.

  • Enhancing the corridor with aesthetic elements such as landscaping and lighting.

  • Relocating some power lines underground or to new overhead locations.

Quick Facts

  • Contractor notice to proceed date: May 1, 2025
  • Contract completion date: Oct. 12, 2028
  • Construction contract value: $67 million
  • Total project cost: $85 million