This project includes design and construction of improvements to alleviate widespread flooding due to moderate rain events impacting the Church Point, Thoroughgood, and adjacent neighborhoods, along with portions of Pleasure House Road and Northampton Boulevard US13.
Improvements include new large storm drain pipes, a stormwater pump station, roadway improvements, and a new wet pond.
The improvements must be phased to prevent adverse downstream impacts:
Phase 1A - BMP and Church Point Drainage Improvements
- New large storm drainpipes and structures.
- New wet pond.
Phase 1B - Pleasure House Rd and Northampton Blvd culvert improvements
- New large storm drainpipes and structures.
- New culvert crossing under Shore Drive.
- New larger culvert crossings under Pleasure House Road and Northampton Boulevard.
- Improvements between Pleasure House Road and Northampton Boulevard.