Project Status and Funding Source

As of August 2025, notice to proceed (NTP) was given to the design-build team in June 2025 and planning has begun. The first effort of the design phase will be to evaluate alternatives for the access route.

This project was funded by CIP 100595.

This project includes the design and construction of a large-scale stormwater pump station (375 cubic foot per second capacity) and associated improvements with an outfall at/near to the shoreline of the Chesapeake Bay adjacent to Lake Bradford/Chubb Lake.

Want more information?

Sign up to receive email updates on the Lake Bradford – Chubb Lake Master Program. Or for more project-specific information, check out the Flood Protection Program’s Monthly Status Reports, which can be found on the Flood Prevention Bond Referendum Oversight Board’s page.