Project Status

Current Status & Next Steps

As of September 2024, the project's design phase is currently 95% complete. The construction phase is planned to begin in April 2028 and is expected to be completed in February 2029. This project is funded by Capital Improvement Project (CIP) 100391.

Purpose of the Project

The pollutant reduction achieved by this project will be applied towards implementation of the City's local phosphorus total maximum daily load action plan.

How the Project Improves Water Quality

This project will install a manufactured treatment device (MTD) to intercept untreated stormwater from an existing 42-inch stormwater pipe along Glen Lochen Drive. The MTD will remove trash, sediment, and nutrients from stormwater runoff before it is discharged into Salem Canal.

Quick Facts

Project Cost

Design:

$250,000

Private Utility Relocations:

$60,000

Construction:

$2,405,000

Total:

$2,715,000

Project Schedule

Design:

July 2023 to October 2024

Private Utility Relocations:

November 2026 to March 2027

Construction:

April 2028 to February 2029

Project Pollutant Removal Benefits

Total phosphorus removal:

13 pounds per year