Centerville Turnpike Phase II
This project widens 1.85 miles of Centerville Turnpike from two to four lanes between Indian River Road and Kempsville Road.

This project widens 1.85 miles of Centerville Turnpike from two to four lanes between Indian River Road and Kempsville Road.
The purpose of this project is to construct a new four‑lane divided highway from Indian River Road to Kempsville Road, improving mobility, safety and overall traffic operations in the Centerville area.
These upgrades will help address current and future congestion on a roadway that already operates over capacity and is projected to see significant growth by 2040.
Key elements of the project include:
Activity
Start
Finish
Cost
Activity
Design
Start
September 2013
Finish
December 2025
Cost
$3,137,385
Activity
Site acquisition
Start
May 2022
Finish
February 2026
Cost
$5,598,450
Activity
Private utility adjustments
Start
February 2026
Finish
December 2026
Cost
$2,650,000
Activity
Construction
Start
January 2027
Finish
July 2030
Cost
$55,007,806
Activity
Inspections and support
Start
January 2027
Finish
July 2030
Cost
$7,342,056
Activity
Tree mitigation
Start
January 2027
Finish
July 2030
Cost
$327,467
Activity
Contingencies
Start
September 2013
Finish
July 2030
Cost
$7,092,578
Cost
Total: $81,155,742