Project Scope
This project constructs new storm drain piping with additional larger drainage inlets, along South Plaza Trail, from South Rosemont Road to Presidential Boulevard, and along Presidential Boulevard to the Windsor Woods Canal.
Construction began in July 2023 and will last about two years. Trident Civil is the contractor.
As with similar projects, lane and road closures will be necessary to complete this work. Street parking within the work zone is not permitted to safeguard residents and facilitate Contractor operations.
Detours will be clearly marked with plenty of signage on site in advance. As work progresses, detour signage will adjust accordingly.
Construction continues between Rosemont Road and Presidential Boulevard. Existing businesses, the Windsor Woods Library, and Fire/EMS Station No. 16 remain open as well as residential access. Please take your time to establish the best route relative to where the Contractor is working at the time.
Silina Drive continues to be the primary detour route with a portion of South Plaza Trail closed.
The contractor completed paving operations work on Presidential Boulevard between Silina Drive and South Plaza Trail and is now performing construction on South Plaza Trail between Rosemont Road and Presidential Boulevard.
The contractor is currently performing work at the intersection of Presidential Boulevard and South Plaza Trail following the completion of the installation of a 12-inch sanitary sewer force main betterment between Rosemont Road and Presidential Boulevard.
With the completion of water, sanitary sewer, and storm drainage improvements, Trident began the concrete work along Presidential Boulevard between Silina Drive and South Plaza Trail. Concrete work includes curb and gutter, sidewalks, ADA ramps, and driveway aprons. This establishes a perimeter that will be used to reconstruct the new roadway pavement section.
The contractor continued with the storm drain installation, transitioning from Presidential Boulevard into the intersection with South Plaza Trail.
The contractor is continuing the installation of the elliptical 91-inch x 58-inch (72-inch circular equivalent) storm drain along Presidential Boulevard to a new storm junction box excavation pit.