Project Status and Funding Source

The project was completed in December 2025 and provides drainage improvements for Windsor Woods Lake and the Windsor Woods neighborhood.

The project was funded by CIP 100488.

Project Scope

This is the first of the three tide gates that will assist in reducing tidal impacts and provide critical stormwater storage needed to mitigate flooding in Windsor Woods, Princess Anne Plaza, and The Lakes. The tide gate (which consists of four individual gates/gate bays) will close during storms to prevent flooding in Windsor Woods from downstream high tides and storm surges. 

The project also includes interim stormwater pumps to help reduce flooding from upstream areas due to extreme rainfall and assist in managing the stormwater. These interim pumps have a capacity of 50 cubic feet per second (50 cfs) and will ultimately be replaced by the future permanent Windsor Woods Pump Station (with 750 cfs pumping capacity).

Want more information?

Sign up to receive email updates on the Flood Protection Program projects in Windsor Woods, Princess Anne Plaza and The Lakes. Or for more project-specific information, check out the Flood Protection Program’s Monthly Status Reports, which can be found on the Flood Prevention Bond Referendum Oversight Board’s page.