First Colonial Road and Oceana Boulevard Drainage Improvements
Constructing a stormwater management facility on City-owned property between New York Avenue and Southern Boulevard to divert stormwater and provide additional runoff storage. The facility will slowly release the stormwater back into the South Oceana Boulevard stormwater pipes further downstream.
Seatack Neighborhood Drainage Improvements
Installing approximately 800 linear feet of 36-inch storm sewer pipe along South Birdneck Road, between Jackson Street and Sea Street, replacing the existing 24-inch and 30-inch pipes that currently collect runoff along South Birdneck Road and from the Seatack neighborhood. Approximately 665 linear feet of 48-inch storm sewer pipe is proposed to replace the existing 36-inch pipe along Jackson Street.