Project Status

Current Status & Next Steps

The project design has been completed, and the environmental permits have been obtained. Construction is expected to begin early to mid-2026. The project has also been approved for a Stormwater Local Assistance Fund (SLAF) grant to cover approximately 75% of the project cost with the balance being funded by Capital Improvement Project (CIP) 100032. A public meeting for the project was held 9/28/2023.

Purpose of the Project

The lake improvements will help remove pollutants from stormwater runoff discharged to the lake, and the pollutant removal benefits will be credited toward the City's requirement under the Chesapeake Bay Total Maximum Daily Load.

How the Project Achieves Purpose

This project will create two new sediment forebays that will capture sediment and pollutants from stormwater runoff before it flows to the main body of the lake. In addition to the forebays, new wetlands areas and an aquatic bench will be constructed to remove stormwater pollutants via natural physical, chemical, and biological processes.

Quick Facts

Project Cost

Design:

$350,000

Construction:

$1,450,000

Total:

$1,800,000

Project Schedule

Design:

March 2023 to November 2025

Construction:

June 2026 to August 2027

Project Pollutant Removal Benefits

Total phosphorus removal:

35 pounds per year

Total nitrogen removal:

125 pounds per year