Project Status

Current Status & Next Steps

The construction project has been awarded, and construction is scheduled to begin in September 2025. The project is funded by Capital Improvement Project (CIP) 100264.

Purpose of the Project

This project will support beneficial uses of local waterways, such as swimming and fishing. The project will be constructed in the Oceana Gardens neighborhood adjacent to Sykes Avenue. The constructed wetlands will treat stormwater from the commercial area west of Sykes Avenue. The wetlands will improve water quality to the Lynnhaven River.

How the Project Achieves Purpose

The project will install a constructed wetlands stormwater management facility. The constructed wetlands will provide wildlife habitat and improve water quality through the incorporation of the following features that will help remove sediment and excess nutrients from stormwater runoff:

  • Pretreatment forebay - allows sediment to settle out.
  • Two wetlands cells - provide habitat, sediment capture, and nutrient removal.
  • Native plants - take up excess phosphorus and nitrogen.

Quick Facts

Project Cost

Design:

$400,000

Construction:

$970,000

Total:

$1,370,000

Project Schedule

Design:

March 2023 to April 2024

Construction:

September 2025 to January 2027

Project Pollutant Removal Benefits

Total phosphorus removal:

13 pounds per year

Total nitrogen removal:

51 pounds per year

Total suspended solids removal:

5,100 pounds per year