Current Status & Next Steps

As of December 2023, the project is in the preliminary design phase with 90% design expected December 2023. This project is funded by Capital Improvement Project (CIP 100391).

Purpose of the Project

The pollutant reduction achieved by this project will be applied toward the implementation of the City’s Local Phosphorous Total Maximum Daily Load Action Plan Implementation.

How the Project Achieves its Purpose

This project will install a manufactured treatment device (MTD) to intercept untreated stormwater from an existing 42-inch stormwater pipe along Sandbridge Road. The MTD will remove trash, sediment, and nutrients from stormwater runoff before it discharges into Ashville Bridge Creek.

Quick Facts

Project Cost

Design:

$190,000

Construction:

$1,255,000

Total:

$1,4455,000

Project Schedule

Design:

November 2023 to December 2024

Construction:

January 2026 to November 2026

Project Pollutant Removal Benefits

Total phosphorus removal:

$3.26 pounds per year