Project Status

Current Status & Next Steps

Design is underway and will be completed by December 2026. The project design is funded by Capital Improvement Project (CIP) 100391.

Purpose of the Project

The project will retrofit an existing volume control pond by adding a forebay and manufactured treatment device (MTD) for pre-treatment, new wetland areas and aeration to improve downstream water quality. The retrofit improvements will reduce pollutants from stormwater runoff before entering the North Landing River.

This project supports the implementation of the City’s Local Total Maximum Daily (TMDL) Phosphorus Action Plan.

How the Project Achieves Purpose

The following features will be incorporated into the project to reduce pollution from stormwater runoff draining from residential properties and local roadways to the pond:

  • Forebay and MTD to pre-treat stormwater runoff and allow silt, debris and other pollutants to settle out of the water before it reaches the lake.
  • Wetland areas to promote sedimentation, allow natural plant uptake of phosphorus and nitrogen, and encourage healthy biological activity.
  • Aeration system to improve oxygen levels that support aquatic life.

Quick Facts

Task

Cost/Duration

Project Cost

Task

Design:

Cost/Duration

$500,000

Task

Site Acquisition:

Cost/Duration

$155,000

Task

Private Utility Adjustment:

Cost/Duration

$185,000

Task

Construction:

Cost/Duration

$4,360,000

Project Schedule

Task

Design:

Cost/Duration

September 2024 to December 2026

Task

Site Acquisition:

Cost/Duration

January 2027 to November 2027

Task

Private Utility Adjustment:

Cost/Duration

November 2027 to November 2028

Task

Construction:

Cost/Duration

April 2033 to April 2035

Project Pollutant Removal Benefits

Task

Total phosphorus removal:

Cost/Duration

41 pounds per year